1. Project Overview:
Project address: China•Xinjiang•Hami
Construction unit: Hami Blue Huoyan New Energy Development Co., Ltd.
Product name: briquette screening and conveying
Production scale: 100,000 tons of briquette production line per year
Service scope: from raw material storage and transportation, screening, transportation to finished product storage and transportation system equipment
2. Project Description
Hami Blue Huoyan New Energy Development Co., Ltd. is a manufacturer of environmentally friendly barbecue charcoal that integrates environmental protection, health and cleanliness. The rich blue charcoal resources in the park can be used as raw materials for production. The company has introduced advanced technology patents. The environmentally friendly barbecue charcoal production line, after being put into operation, can absorb the blue charcoal resources in the park, and at the same time reduce the production cost of the enterprise. It is expected that the output value of the project can be 120 million yuan after completion.
3. Design Principles
(1) On the premise of meeting the requirements of production scale, the host adopts stand-alone, single-line equipment to achieve the purpose of smooth and compact production line, save land, and increase land use rate.
(2) The auxiliary equipment is based on the principles of stability, reliability, and energy saving to ensure normal production, high quality, high yield, and low energy consumption.
(3) Fully integrate the local natural conditions, optimize the design plan under the process and production conditions, and reduce the project cost as much as possible.
(4) Conscientiously implement the relevant national environmental protection, laws, regulations and standards, strictly control environmental pollution, reduce pollutant discharge, protect and improve the environment, and realize safe and civilized production.
4. Project Implementation
After the contract was signed, our company concentrated its strengths and made equipment. With the strong support and cooperation of the owner, the project was put into operation on June 20. After more than 20 days of commissioning, it successfully reached the production standard and was highly praised and affirmed by the owner. .
5. Equipment Used
No | Product Name | Model | Qty. |
1 | Double shaft mixer | ZJ400×6m | 10 Set |
2 | Vibrating screen | YK1230 | 10 Set |
6. Project Photos